VANGUARD LOFTS HAS BEGUN CONSTRUCTION

Tetra Terra Development is proud to announce commencement of construction for Vanguard Lofts. With the excellent work of our project team and the support from the community we are extremely excited to be bringing this development to the Rosemary District. We will upload construction photos and videos to help document and share with the community our progress.

CONSTRUCTION PHOTOS AND VIDEOS

5/29/15 - Tree removal and site scrapping.
5/29/15 - Tree removal and site scrapping.
5/29/15 - Tree removal and site scrapping.
6/23/15 – Vibro compacting the soil.
6/23/15 – Vibro compacting the soil.

        6/23/15 – VIBRO COMPACTING THE SOIL.

9/24/15 – Final site preparation and grading.
9/24/15 – Final site preparation and grading.
9/24/15 – Final site preparation and grading.
10/9/15 – Foundation excavation and footings.
10/9/15 – Foundation excavation and footings.
10/9/15 – Foundation excavation and footings.
10/23/15 – Concrete footings being poured.
10/23/15 – Concrete footings being poured.

        10/23/15 – Concrete footings being poured.

10/23/15 – Concrete block wall construction.
10/23/15 – Concrete block wall construction.
12/4/15 – Ground floor electrical and plumbing rough in.
12/4/15 – Ground floor electrical and plumbing rough in.
12/4/15 – Ground floor electrical and plumbing rough in.
12/22/15 – Ground floor concrete slab preparation.

        12/22/15 – Ground floor concrete slab preparation.

1/8/16 – Ground floor concrete slab pour.
1/8/16 – Ground floor concrete slab pour.
1/16/16 – First floor concrete block wall construction.
1/16/16 – First floor concrete block wall construction.
1/16/16 – First floor concrete block wall construction.

        1/23/16 – First floor concrete block wall construction.

1/23/16 – First floor concrete block wall construction and form work.
1/23/16 – First floor concrete block wall construction and form work.
1/23/16 – First floor concrete block wall construction and form work.
2/1/16 – First floor concrete columns, headers and tie beam pour.
2/1/16 – First floor concrete columns, headers and tie beam pour.
2/1/16 – First floor concrete columns, headers and tie beam pour.
2/15/16 – Garden Unit front concrete and masonry complete.
2/15/16 – Garden Unit front concrete and masonry complete.
2/15/16 – Garden Unit rear concrete and masonry complete.
2/15/16 – Garden Unit rear concrete and masonry complete.
2/15/16 – Exposed concrete exterior stair first floor complete.
2/15/16 – Garden Unit living room to master bedroom interior view.
2/15/16 – Garden Unit master bedroom to living room interior view.
2/15/16 – Garden Unit master bedroom corner window detail.
4/28/16 – Exposed precast concrete stair installation.
4/28/16 – Exposed precast concrete stair installation.
5/8/16 – First floor steel installation.
5/8/16 – First floor steel installation.
5/8/16 – First floor steel installation.
5/11/16 – Second floor concrete plank installation.
5/11/16 – Second floor concrete plank installation.
5/11/16 – Second floor concrete plank installation.
6/13/16 – Second floor concrete and masonry installation.
6/13/16 – Second floor concrete and masonry installation.
6/13/16 – Second floor concrete and masonry installation.
6/13/16 – Second floor concrete and masonry installation.
6/23/16 – Exposed precast concrete stair installation.
6/23/16 – Exposed precast concrete stair installation.
7/15/16 – Third floor concrete plank installation.
7/15/16 – Third floor concrete and masonry installation.
7/15/16 – Third floor concrete and masonry installation.
7/22/16 – Second floor structural steel installation.
7/22/16 – Second floor structural steel installation.
7/22/16 – Second floor structural steel installation.
8/4/16 – Fourth floor concrete plank installation and third floor concrete and masonry complete.
8/4/16 – Fourth floor concrete plank installation and third floor concrete and masonry complete.
8/4/16 – Fourth floor concrete plank installation.
8/4/16 – Fourth floor concrete plank installation.
8/18/16 – Fourth floor concrete and masonry installation.
8/18/16 – Fourth floor concrete and masonry installation.
8/18/16 – Underground vault concrete and masonry installation.
8/26/16 – Underground vault/garage concrete plank installation.
8/26/16 – Second floor structural steel complete.
8/26/16 – Second floor structural steel and precast stair complete.
8/26/16 – Fourth floor concrete and masonry complete.
9/25/16 – Fourth floor roof canopy steel beam installation.
9/25/16 – Fourth floor roof canopy steel beam installation.
9/25/16 – Fourth floor roof canopy steel beam installation.
11/8/16 – Utilities and city water tap.
11/8/16 – Utilities and city water tap.
12/28/16 – First floor insulation and metal framing.
12/28/16 – First floor insulation and metal framing.
12/28/16 – First floor insulation and metal framing.
1/20/17 – First floor insulation and metal framing complete.
1/20/17 – First floor insulation and metal framing complete.
1/20/17 – First floor insulation and metal framing complete.
2/1/17 – Second floor insulation and metal framing.
2/1/17 – Second floor insulation and metal framing.
2/10/17 – Third floor insulation and metal framing.
2/10/17 – Third floor insulation and metal framing.
2/21/17 – First floor electrical rough in.
2/21/17 – Exterior metal framing.
2/21/17 – Exterior metal framing.
3/01/17 – Exterior metal framing.
3/01/17 – Exterior metal framing.
3/01/17 – Exterior metal framing.
3/17/17 – Fourth floor metal framing.
3/17/17 – Fourth floor metal framing.
3/17/17 – West precast concrete stair installation.

        3/31/17 – Interior steel stair stringer installation.

3/31/17 – Interior steel stair stringer installation.
3/31/17 – Third floor interior metal framing.
3/31/17 – Third floor interior metal framing.
4/6/17 – Interior steel stair from rooftop terrace.
4/6/17 – Third floor patio box exterior metal framing.
4/6/17 – Third floor patio box exterior metal framing.
4/20/17 – Exterior metal framing complete.
4/20/17 – Exterior metal framing complete.
4/20/17 – Exterior metal framing and trusses complete.
4/20/17 – Garage metal trusses complete.
4/20/17 – Garage metal trusses complete.
4/31/17 – Metal roof deck complete.
4/31/17 – Metal roof deck complete.
4/31/17 – Interior metal framing complete.
4/31/17 – West exposed precast concrete stair complete.